{"_buckets": {"deposit": "c0c9f101-dd00-4355-808b-725c0791cb86"}, "_deposit": {"created_by": 20, "id": "8587", "owner": "20", "owners": [20], "owners_ext": {"displayname": "", "username": ""}, "pid": {"revision_id": 0, "type": "depid", "value": "8587"}, "status": "published"}, "_oai": {"id": "oai:meral.edu.mm:recid/00008587", "sets": []}, "author_link": [], "control_number": "8587", "item_1583103067471": {"attribute_name": "Title", "attribute_value_mlt": [{"subitem_1551255647225": "Analysis of Constraints on Construction Projects of Yangon Regional Health Department (For Budget Year 2018-2019) (Yan Naung Tun, 2022)", "subitem_1551255648112": "en"}]}, "item_1583103085720": {"attribute_name": "Description", "attribute_value_mlt": [{"interim": "This study was done on tender process of government construction projects\nunder Yangon Regional Public Health and Medical Care services Department aiming\nto explore the constraints of construction projects for fiscal year (2018-2019). A\ncross-sectional study was done by secondary data reviews from Yangon Regional\nHealth Department Reports of fiscal year 2018-2019. For primary data collection, five\nin-depth interview sessions were performed and purposive sampling method was\napplied. As regards to results, completion of the constructions projects for fiscal year\n(2018-2019), only 44.76% of constructions project under Yangon Regional Medical\nServices Department and 76% of construction project under Yangon Regional Public\nHealth Department had finished 75-100% of construction work. As regards to\nduration between tender calling process to actual starting time of construction work\nwas ranging from 161 days to 229 days, mean was 196 days for one fiscal year.\nTherefore, the operational construction time of projects for one fiscal year was six\nmonths. Qualitative assessment revealed the constraints such as very limited\npreparation time, inadequate information for construction projects, unsystematic\ndesign modification and extra works, low Per Area Estimation, weakness in financial\nmanagement, unable to monitor the quality of construction due to limited resources.\nRecommended to improve current rules and regulations regards to government tender\nprojects and need to condense the overlapping steps to shorten the duration of process."}]}, "item_1583103120197": {"attribute_name": "Files", "attribute_type": "file", "attribute_value_mlt": [{"accessrole": "open_access", "date": [{"dateType": "Available", "dateValue": "2022-12-29"}], "displaytype": "preview", "download_preview_message": "", "file_order": 0, "filename": "Yan Naung Tun, EMPA-26, 17th Batch.pdf", "filesize": [{"value": "734 KB"}], "format": "application/pdf", "future_date_message": "", "is_thumbnail": false, "licensetype": "license_0", "mimetype": "application/pdf", "size": 734000.0, "url": {"url": "https://meral.edu.mm/record/8587/files/Yan Naung Tun, EMPA-26, 17th Batch.pdf"}, "version_id": "d48c32eb-470f-402a-97ae-952ee0381b50"}]}, "item_1583103233624": {"attribute_name": "Thesis/dissertations", "attribute_value_mlt": [{"subitem_awarding_university": "Yangon Univerisity of Economics", "subitem_supervisor(s)": [{"subitem_supervisor": "U Thein Naing"}]}]}, "item_1583105942107": {"attribute_name": "Authors", "attribute_value_mlt": [{"subitem_authors": [{"subitem_authors_fullname": "Yan Naung Tun"}]}]}, "item_1583108359239": {"attribute_name": "Upload type", "attribute_value_mlt": [{"interim": "Other"}]}, "item_1583108428133": {"attribute_name": "Publication type", "attribute_value_mlt": [{"interim": "Thesis"}]}, "item_1583159729339": {"attribute_name": "Publication date", "attribute_value": "2022-10-01"}, "item_title": "Analysis of Constraints on Construction Projects of Yangon Regional Health Department (For Budget Year 2018-2019) (Yan Naung Tun, 2022)", "item_type_id": "21", "owner": "20", "path": ["1582965722087"], "permalink_uri": "https://meral.edu.mm/records/8587", "pubdate": {"attribute_name": "Deposit date", "attribute_value": "2022-12-29"}, "publish_date": "2022-12-29", "publish_status": "0", "recid": "8587", "relation": {}, "relation_version_is_last": true, "title": ["Analysis of Constraints on Construction Projects of Yangon Regional Health Department (For Budget Year 2018-2019) (Yan Naung Tun, 2022)"], "weko_shared_id": -1}
  1. Yangon University of Economics
  2. Master of Public Administrations (MPA/EMPA)

Analysis of Constraints on Construction Projects of Yangon Regional Health Department (For Budget Year 2018-2019) (Yan Naung Tun, 2022)

https://meral.edu.mm/records/8587
https://meral.edu.mm/records/8587
b220c3c3-5ad9-4cb8-91de-0633305ee238
c0c9f101-dd00-4355-808b-725c0791cb86
None
Preview
Name / File License Actions
Yan Yan Naung Tun, EMPA-26, 17th Batch.pdf (734 KB)
license.icon
Publication type
Thesis
Upload type
Other
Title
Title Analysis of Constraints on Construction Projects of Yangon Regional Health Department (For Budget Year 2018-2019) (Yan Naung Tun, 2022)
Language en
Publication date 2022-10-01
Authors
Yan Naung Tun
Description
This study was done on tender process of government construction projects
under Yangon Regional Public Health and Medical Care services Department aiming
to explore the constraints of construction projects for fiscal year (2018-2019). A
cross-sectional study was done by secondary data reviews from Yangon Regional
Health Department Reports of fiscal year 2018-2019. For primary data collection, five
in-depth interview sessions were performed and purposive sampling method was
applied. As regards to results, completion of the constructions projects for fiscal year
(2018-2019), only 44.76% of constructions project under Yangon Regional Medical
Services Department and 76% of construction project under Yangon Regional Public
Health Department had finished 75-100% of construction work. As regards to
duration between tender calling process to actual starting time of construction work
was ranging from 161 days to 229 days, mean was 196 days for one fiscal year.
Therefore, the operational construction time of projects for one fiscal year was six
months. Qualitative assessment revealed the constraints such as very limited
preparation time, inadequate information for construction projects, unsystematic
design modification and extra works, low Per Area Estimation, weakness in financial
management, unable to monitor the quality of construction due to limited resources.
Recommended to improve current rules and regulations regards to government tender
projects and need to condense the overlapping steps to shorten the duration of process.
Thesis/dissertations
Yangon Univerisity of Economics
U Thein Naing
Back
0
0
views
downloads
See details
Views Downloads

Versions

Ver.1 2022-12-29 03:48:49.868643